A gable roof over a 12 × 12 ft building: 6-in-12 pitch, rafters 24 in on center, asphalt shingles. Every part is below, in the order the steps use it. Nails and metal connectors are not listed.
≈2–3 days for a small crew
This guide shows the sequence, not a design. Lumber sizes, spacing and connections come from your plans and local code — check them before cutting anything.
Ceiling joists run wall to wall across the top plates, one at every rafter position. They carry the ceiling and tie the two walls together, so the rafters can’t push them apart.
≈2 hr · 7 joists · 24 in on center
Parts: 7 × Ceiling joist / rafter tie, 2×6 × 14 ft
With a ridge board — not a structural ridge beam — these ties are what keep the walls from spreading. Don’t skip or cut them.
The ridge board runs the full length of the roof at the peak. It gets braced level and plumb until the rafters lock it in place.
≈1 hr · 3 ft rise over a 6 ft run = 6-in-12 pitch
Parts: 1 × Ridge board, 2×8 × 14 ft
The 3 ft rise is measured on the rafter layout line, so the ridge itself sits a little higher than 3 ft above the plates. Sight down the board and set any crown (bow) facing up.
Rafter pairs run from the top plates up to the ridge, one pair at every ceiling joist: seven pairs at 24 in on center, including one at each gable end.
≈4 hr · 7 pairs · 24 in on center
Parts: 14 × Rafter, 2×6 × 8 ft
Set opposite rafters together so the ridge stays centered. Add metal rafter-to-plate ties where the plans call for them. (Most real roofs also run the rafter tails 12–24 in past the wall for an overhang; this model leaves that off.)
Sheets go on with the long edge running across the rafters. The second row is offset 4 ft so the end joints don’t line up, and every end joint lands on a rafter.
≈3 hr · 6 sheets, 4 × 8 ft · 2 rows per side
Parts: 6 × Roof sheathing, 4×8 ft sheet
Leave a 1/8 in gap at every sheet edge so the panels can expand. With rafters 24 in apart, most panels also need metal edge clips (H-clips) between rafters; the panel’s span rating tells you.
Metal drip edge goes along both eaves first, directly on the sheathing, so water running off the roof drips clear of the wall.
≈30 min · 2 eaves · 12 ft each
Parts: 3 × Drip edge, 10 ft piece
At the eaves the drip edge goes under the underlayment. At the rakes it goes over. The order matters.
Synthetic underlayment rolls out in horizontal courses, starting at the eave and lapping each course over the one below. Then drip edge goes up both rakes, over the underlayment.
≈1.5 hr · 2 courses per side · 1 roll
Parts: 1 × Synthetic underlayment, roll; 4 × Drip edge, 10 ft piece
Lap widths and fastener spacing vary by product; follow the instructions printed on the roll. The top course usually runs over the ridge onto the other slope.
A starter strip goes along the eave first. Then the shingle courses work up the slope, each covering most of the one below and leaving about 5⅝ in exposed.
≈1 day · ≈14 courses per side · 5⅝ in exposure
Parts: 1 × Starter strip, bundle; 6 × Architectural shingles, bundle
Exposure, overhang and nail placement come from the shingle wrapper. Follow it exactly, or the manufacturer’s warranty may not apply.
Hip-and-ridge cap shingles fold over the peak and seal the top courses. Start at the end opposite the prevailing wind so each lap points downwind.
≈1 hr · One bundle covers the 12 ft ridge
Parts: 1 × Hip & ridge cap, bundle
If the plans call for a ridge vent, it goes on before the cap.
That’s the roof, start to finish. Check it from the ground: a straight ridge, even courses, and drip edge tight along every edge.