One 30 ft eave gets a seamless 5 in K-style aluminum gutter that drains to a single 2×3 in downspout at the right end. Every part is below, in the order the steps use it. Screws, rivets and hanger screws are not listed.
≈4–6 hr for a small crew
This guide shows the sequence, not a design. Gutter size, the number of downspouts and where they go depend on the roof area draining to them and local rainfall. Your installer sizes them.
Everything hangs from the fascia, the board along the roof edge. It has to be sound and straight before a gutter goes on it.
≈30 min, more if boards need replacing · 30 ft eave · 2×6 fascia
Parts: 1 × Fascia board, 2×6 × 8 ft (only where rotted)
The hanger screws need solid wood behind them. This is also when to confirm the drip edge along the roof edge is in place and sound. The gutter tucks up behind it in step 5.
Gutters aren’t hung dead level. A chalk line on the fascia sets a slight, steady fall toward the downspout end, so water keeps moving instead of sitting.
≈15 min · 30 ft run · ¾ in fall at ¼ in per 10 ft
Parts: 1 × Chalk line (layout tool)
The right fall comes from the gutter manufacturer. About ¼ in per 10 ft is common, and some call for more. It’s too small to see at this scale, and that’s intended: from the street, a gutter should look level.
Seamless gutter is roll-formed on site from a coil of aluminum, in one piece the full length of the eave. On the ground, end caps go on both ends.
≈30 min · 1 piece · 30 ft · no seams along the run
Parts: 1 × Seamless gutter, 5 in K-style aluminum, 30 ft; 2 × End cap, 5 in K-style; 1 × Gutter sealant, tube
With no seams along the run, the joints left to leak are the end caps and the outlet. Seal them with a sealant made for gutters, following the tube.
At the low end, a hole is cut in the gutter bottom and a drop outlet is set into it from inside. The downspout will slide over the outlet’s tube.
≈15 min · 1 outlet · 2×3 in · at the low end
Parts: 1 × Drop outlet, 2×3 in
One downspout is typical for a short run like this. Longer runs (often past about 35–40 ft) or larger roof areas get a downspout at each end, with the gutter pitched from the middle toward both. Your installer works it out from the roof area and local rainfall.
The gutter goes up in one piece. Its back slides up behind the drip edge, so water coming off the roof lands inside the gutter, and its top follows the chalk line.
≈45 min · 15 hangers · 24 in on center · first and last 12 in from the ends
Parts: 1 × Seamless gutter, 5 in K-style aluminum, 30 ft; 15 × Hidden hanger with screw
A 24 in spacing is common. Follow the gutter and hanger manufacturer, and space them closer where they call for it. Screws go into solid fascia, and into the rafter tails behind it where they line up.
Two elbows carry the water from the outlet back under the eave to the wall. From there the downspout runs straight down, strapped to the wall.
≈45 min · 2 elbows · ≈6 ft drop · 3 straps
Parts: 2 × Elbow, 2×3 in; 1 × Downspout, 2×3 in aluminum, 10 ft length; 3 × Downspout strap
Each upper piece fits inside the one below it, so water can’t run out at a joint. Fasten every joint with short screws or rivets. Strap spacing varies by product; follow the downspout maker.
At the bottom, an elbow turns the water away from the house, and an extension carries it out onto a splash block.
≈20 min · Discharge ≈5 ft from the wall, measured from the wall face
Parts: 1 × Elbow, 2×3 in; 1 × Extension, cut from downspout stock; 1 × Splash block
Many guides call for about 5 ft, and code requires at least that where soils are expansive, unless the water goes into an approved drain. Check your local code, and make sure the ground slopes away from the house.
That’s one eave, start to finish. Run a hose into the high end: water should reach the outlet with no drips at the caps, outlet or joints.