Two common ways to put a building on the ground, side by side on one lot. On the left, a slab-on-grade: a concrete slab with a thickened edge that works as its footing. On the right, a raised foundation: a perimeter footing and short concrete stem wall, two interior piers with posts and a girder, and a wood floor over a crawlspace. Each one is 16 × 20 ft. The parts are below, in the order the steps use them.
≈2–4 weeks of site and foundation work for a small building like this, after plans and permit
This guide shows the sequence, not a design. Footing sizes, rebar, concrete strength, anchor bolts and hold-downs come from your approved plans and the soils report. Check them before you dig.
A new foundation starts on paper. The engineer’s plans show the footings, the steel and the connections. In much of Southern California the city also wants a soils (geotechnical) report: it says how much load the ground can carry, whether the soil swells when it gets wet, and how the pad has to be prepared. The building department approves it all before any digging.
≈2–6 months for the soils report, engineering and permit, depending on the city · Plans + soils report · permit before any digging
Parts: 1 set × Plans, soils report and permit
Expansive clay is common in Southern California. It is one reason footings here are often deeper and more heavily reinforced than the code minimum. The plans and soils report govern.
Before any grading, the corners and the edges of the pad are rough-staked from the plans so the crew knows where to cut. Then the topsoil, roots and debris come off, because organic soil keeps settling. The pad is cut or filled to the heights on the plans, checked with a laser level from a fixed benchmark, and compacted in thin layers.
≈1–2 days · Topsoil stripped · pad graded and compacted
Parts: 1 × Laser level (sets grades); 2 × Plate compactor; 6 × Compaction test spot
Soils reports often call for a specific compaction, commonly 90% relative compaction, and for the soils engineer to test or observe it. Finished grade around a building should fall away from it, typically 6 in over the first 10 ft.
With the pad graded, the corners are measured in from the property lines using the dimensions on the plans and marked with stakes. Batter boards go up a few feet outside each corner, and string lines stretched between them mark the outside face of each foundation. The strings stay put while the corner stakes come out for digging.
≈half a day · 8 corners · strings on the outside face of each foundation
Parts: 8 × Corner stake (hub); 8 × Batter boards, one set per corner; 2 sets × String lines (outside face of the foundation)
Some cities, or the plans, require a licensed land surveyor to set or verify the property corners or the building location before the foundation inspection.
The footing trenches are dug to the width and depth on the plans: here 12 in wide and 18 in below grade, all the way around each building. The raised foundation also gets two square holes for the interior piers. Loose soil is cleaned out of the bottoms.
≈1–2 days · Perimeter trenches 12 in wide × 18 in deep · 2 pier holes 24 × 24 in
Many soils reports require the engineer to see the trenches before any steel goes in. In expansive soil, footings are often deeper and wider than this example.
On a slab, the drain lines go in now, because they end up under the concrete. They are laid in shallow trenches in the pad at a steady slope toward the building drain, which leaves through a sleeve in the footing. Each fixture gets a capped stub that will stick up through the slab.
≈1–2 days, plus the inspection · Drain lines + fixture stubs · underground plumbing inspection
Parts: 1 set × Drain lines and fixture stubs (ABS); 1 × Pipe sleeve through the footing
On the raised foundation, plumbing runs later in the crawlspace, where it stays reachable. In many Southern California homes the water lines run overhead instead of under the slab.
The slab gets 2×12 form boards around its edge, staked and braced, with their tops at the finished slab height. The raised foundation’s stem wall gets plywood forms on both faces, with blockouts for the screened crawlspace vents and the access opening cast right into the wall.
≈1–2 days · Slab: 2×12 edge forms · Raised: stem forms, 6 vents, 1 access opening
Parts: 4 × Slab form board, 2×12; 36 × Form stake, 2×4; 11 × Stem-wall form panel, ¾ in plywood; 6 × Screened foundation vent; 1 × Crawlspace access opening, 24 × 16 in
Crawlspaces commonly need at least 1 sq ft of net vent area for every 150 sq ft of crawlspace, with a vent within 3 ft of each corner, and an access opening at least 16 × 24 in through a perimeter wall. Here: 320 sq ft ÷ 150 ≈ 2.1 sq ft, so six vents with at least 0.36 sq ft (about 52 sq in) of net free area each; the net area is printed on the vent. Rebar is kept out of vent and access openings, and the plans may call for extra bars around them. Your plans and local code set the actual numbers.
Inside the slab forms, 4 in of clean gravel goes down over the compacted pad, then a heavy plastic vapor retarder with taped laps. Together they keep ground moisture from wicking up into the slab and the floors on it.
≈half a day · ≈3.5 yd³ of gravel · ≈350 sq ft of 15-mil vapor retarder
Parts: ≈3.5 yd³ × Gravel base (capillary break), 4 in; ≈350 ft² × Vapor retarder, 15-mil
California’s green building code generally calls for a 4 in base of ½ in or larger clean aggregate under slabs, with a vapor retarder in direct contact with the concrete, unless the engineer designs another way. 15-mil is a common choice; the plans say what to use.
The steel goes in next. The footings get continuous bars top and bottom; the slab gets a grid of bars held up on small concrete blocks (dobies) so it ends up inside the concrete; the stem wall gets horizontal and vertical bars. Anchor bolts and hold-down anchors are set exactly where the walls and floor will need them.
≈1–2 days, plus the pre-pour inspection · Slab grid #4 @ 18 in each way · 67 bars (about 10% extra) · 36 anchor bolts · 8 hold-downs · pre-pour inspection
Parts: 67 × Rebar, #4 × 20 ft; 36 × Anchor bolt, ½ in (size per plans); 8 × Hold-down anchor (where the plans call for them); 2 × Ufer ground (concrete-encased electrode) stub
Before any concrete is ordered, the inspector checks the forms, the steel and its clearances, the anchor bolts and hold-downs, the vapor retarder and the Ufer ground. Bar sizes and spacing here are a typical example; the plans set them.
Ready-mix concrete is placed from the truck or a pump, consolidated around the steel, and struck off level. The slab is floated and troweled smooth; the tops of the stem walls are leveled to the form lines.
≈1 day · Slab ≈9.5 yd³ · raised ≈6 yd³ (each about 10% extra)
Parts: ≈15.5 yd³ × Concrete, ready-mix
Hot, dry, windy days pull water out of fresh concrete fast. Crews pour early and keep the new concrete damp while it cures.
The concrete is kept damp while it cures. After a few days the forms come off, leaving the vents and the access opening cast into the stem wall. Concrete keeps gaining strength for weeks; it reaches its design strength at about 28 days.
≈3–7 days · Forms off after ≈3–7 days, per the plans
How soon framing can start on new concrete is up to the engineer and the plans. Cracks, honeycombing or a misplaced bolt get looked at now, while fixes are easy. Every scrap of form lumber and wood debris comes out of the crawlspace before the floor goes on: the code requires it, and leftover wood draws termites.
A pressure-treated wood sill is drilled over the anchor bolts, set on the concrete and bolted down with square plate washers and nuts. On the slab, the walls are built up from this sill. On the raised foundation, the floor framing sits on it.
≈half a day · Slab: 2×4 PT sill · Raised: 2×6 PT sill · 36 plate washers
Parts: 8 × Mudsill, pressure-treated; 36 × Square plate washer and nut
Southern California sits near the San Andreas Fault and many smaller faults, and these bolted connections are a big part of what keeps a house on its foundation in an earthquake. Anchor bolts here get square plate washers, commonly 3 × 3 in, under the nuts. Sill size, washer size and bolt spacing come from the plans; on slabs the wall framers often set the sill as they build the walls.
Inside the crawlspace, a steel post base is fastened to each pier, a short pressure-treated post stands in it, and a 4×8 girder runs front to back on top of the posts. Its ends sit on a pressure-treated shim in pockets cast into the stem walls, with about ½ in of air space at the sides and end so the wood stays dry, and at least 3 in of bearing. Its top lines up with the top of the sill.
≈half a day · 2 posts · 1 girder · spans of about 6½ ft between supports
Parts: 2 × Post base; 2 × Post, 4×4 pressure-treated; 2 × Post cap; 2 × Bearing shim under each girder end, pressure-treated; 1 × Girder, 4×8 × 20 ft (pressure-treated where the plans call for it)
Wood closer than 18 in to the ground under joists, or 12 in under girders, has to be pressure-treated or naturally durable. Here the girder sits just over 12 in up. Girder size and post spacing come from the plans.
Rim joists go around the edge on the sill. Floor joists run from the rim to the girder at 16 in on center, toenailed to the sill and girder. Where joists from the two sides meet over the girder they’re tied together with a metal strap or wood splice (or lapped and nailed), and solid blocking keeps them from rolling.
≈1 day, plus the underfloor inspection · 2×8 joists @ 16 in o.c. · 28 joists (31 ordered) · 4 rim/end joists · 15 blocks
Parts: 4 × Rim and end joists, 2×8; 31 × Floor joist, 2×8 × 8 ft; 14 × Joist tie over the girder (strap or splice); 15 × Solid blocking, 2×8
Many cities inspect the raised-floor framing, plus any floor insulation, plumbing and ducts in the crawlspace, before the subfloor covers it. Joist size, span and nailing come from the plans, which may also call for metal framing clips tying the rim to the sill.
Tongue-and-groove plywood goes on with its long side across the joists, glued to every joist and nailed off. The end joints are staggered and always land on a joist. With that, the raised floor is ready for walls, just like the slab next door.
≈half a day · 11 sheets of 23/32 in T&G plywood (10 needed, about 10% extra)
Parts: 11 × Subfloor, 23/32 in tongue-and-groove plywood
Leave the small gap between sheets that the panel maker calls for. Nail size and spacing come from the nailing schedule on the plans.
Two foundations, start to finish: a slab-on-grade poured in one piece over gravel and a vapor retarder, and a raised floor on a perimeter stem wall, piers and a girder. Both are tied down with anchor bolts and hold-downs, ready for the walls.